Visual Library

Photos, renderings & videos.

Follow the project visually through renderings, design concepts, construction photos and future progress galleries.

Featured exterior renderings

Spaces shared in the June 10, 2026 community presentation.

Main entry drive — front elevation
Aerial rendering — full site overview
Site aerial — building and grounds
Bus drop-off and arrival
Interior courtyard

Construction progress

Photographs from the site, organized by month with the most recent first.

October 2026 — Structural steel columns and metal decking in place at Stepping Stones wing, with underground plumbing stubbed up below
October 2026 — Steel framing rising above the waterproofed foundation walls alongside the existing school
October 2026 — Aerial lift crews bolting steel beams and connections beneath the new main level framing
October 2026 — Waterproofed foundation walls along the existing gym, with the crane setting steel beyond
October 2026 — Underground electrical conduit runs rising at the base of the lower-level foundation walls
October 2026 — Excavator trenching for under-slab drainage and utility lines across the building pad
October 2026 — Gravel base, vapor barrier and perimeter insulation laid out in preparation for the floor slab
October 2026 — Stepped concrete foundation walls and formwork for the gymnasium and cafeteria area
October 2026 — Completed foundation walls backfilled with stone, ready for slab preparation
October 2026 — Long Lots students listen as the Construction Manager and project team explain the equipment at work on the new building
October 2026 — Building committee, school superintendent, district leaders, Construction Manager and Architect with Leo the Lion after the update to students and the school staff.
October 2026 — Project team, school staff and Leo the Lion, after the update to students and the school staff.
September 2026 — Foundation wall formwork and underground utility work progressing near the northeast corner.
September 2026 — Underground plumbing and utility lines installed across the building footprint ahead of slab preparation
September 2026 — Reinforcing steel and formwork prepared at gymnasium entrance
September 2026 — Concrete foundation walls with formwork and bracing stacked at the southwest corner near future Stepping Stones entrance
September 2026 — Foundation footings and rebar installation alongside the existing school, with the terraced slope covered for erosion protection
September 2026 — Full-site panorama showing the graded construction road, foundation perimeter and equipment staged across the building footprint
August 2026 — 360° view between the existing school wings and formed foundation walls
August 2026 — Completed concrete foundation walls with waterproofing membrane applied, viewed from the excavated slope behind the entrance to the existing bus loop. 
August 2026 — Wide view of the foundation and waterproofed walls at the southeast corner of the new building
August 2026 — Bundled conduit and utility piping staged across the graded pad ahead of underground installation
August 2026 — Full-site panorama showing footings, concrete pads and heavy equipment working the length of the new building footprint
July 2026 — Cast concrete pier and braced wall formwork on terrace three
July 2026 — Foundation walls forming and rebar installation
July 2026 — Foundation footing and rebar inspection on the north wing
July 2026 — Poured footings and rebar alongside the existing school
June 2026 — Site excavation on terrace three
May 2026 — Earthwork underway at existing baseball field. 
October 2025 — First Selectwoman, Superintendent, Principals and LLSBC with Leo the Lion 
October 2025 — LLSBC Members: Tim Wetmore, Jay Keenan, Don O'Day, Leo the Lion, Sri Puttagunta and Joe Renzulli
October 2025 — Town officials and board members line up with ceremonial shovels and Leo the Lion
October 2025 — Building committee members and BOE town leaders after the ceremony
October 2025 — Long Lots families, PTA volunteers and Leo the Lion celebrate the start of construction
October 2025 — Groundbreaking ceremony with Long Lots students and Leo the Lion

Interior design concepts

Spaces shared in the June 10, 2026 community presentation.

Main Lobby
Cafeteria
Gymnasium
Media Center
Main Street Corridor
Multipurpose Room
K–5th Grade Classroom Corridor
Stepping Stones Classroom Corridor
Stepping Stones Classroom
Kindergarten Classroom
Typical Grade Level Classroom
Break-Out Nook