Construction Updates as of October 23, 2026
Steel is rising in the Stepping Stones wing while crews finish the last foundation pours, waterproofing and underground work ahead of the first-floor slab.
What crews are doing right now
- Erecting steel and metal decking in the Stepping Stones wing of the building.
- Continue installation of remaining foundations and backfilling, elevator shaft, waterproofing and insulation to complete the Gymnasium, Multipurpose and Cafeteria.
- Roughing in underground electric, under slab drainage, plumbing and fire protection prior to the pouring of the first-floor slab.
Underground and sitework
- Continuation of all underground utilities on the lower-level for water, electric, sanitary and fire service water mains.
- Continued installation of stormwater structures on the north side of terrace four.
- Start of excavation and grading of the northerly storm water retention basin.
What families will notice
- The building is starting to take shape as the steel installation continues.
- The elevator shaft rising to the West adjacent to the Gymnasium and Multipurpose rooms.
- Excited students and staff after presentation by the Architect and Construction Manager.
- Steel beam for students to sign which will be hoisted up into the building.
Coming up next
- Remaining foundation pours for the cafeteria and Gymnasium should wrap up in the next few weeks.
- Elevator CMU walls to be installed.
- Complete prep for Lower-level floor slab pours expected to begin in November.
- Erection of Structural steel and installation of metal decking to continue.
Source: Newfield Construction Group. Dates are projections and can shift with site conditions and inspections.
Next update
Late November
2026