The new Long Lots Elementary School and Stepping Stones Preschool is in active construction. Below is the construction timeline, organized by project phases, followed by the latest updates from the field.

Construction Timeline

From shovel to first day of school

Click through for a high-level overview of the major phases of a new school build.

Newfield Construction estimates the new building phase will take approximately 20 months, with student move-in projected for January 2028 and completion of site improvements and playgrounds by August 2028.

12345678910
Ironworker sitting on a steel beam bolting a connection as the school's steel frame and roof trusses rise
Milestone 5 of 10In progress

Structural Framing

  • Steel beams and masonry walls rise.
  • Roof trusses are securely bolted.
  • Crews celebrate installation of the highest beam with children's signatures.

Know the site

Get your bearings

These drawings help make sense of what neighbors and families see from the road. Click any map to view it full screen.

Existing conditions and terraces

The property steps down in elevation as you go from the South to the North (looking from left to right from Hyde Lane), from the former community gardens on terrace 1, to the existing parking and school on terrace 2, to the existing baseball and soccer fields on terrace 3, to the lower soccer fields on terrace 4.

Site plan with existing and new school

This drawing overlays the existing building footprint on the future school site, so you can see how the new school sits on the site while the existing building stays in use through construction.

Construction Updates

Notes from the field

A plain-language summary of site activity, refreshed every month.

Page 1 of 3

Construction Updates as of October 23, 2026

Steel is rising in the Stepping Stones wing while crews finish the last foundation pours, waterproofing and underground work ahead of the first-floor slab.

What crews are doing right now

  • Erecting steel and metal decking in the Stepping Stones wing of the building.
  • Continue installation of remaining foundations and backfilling, elevator shaft, waterproofing and insulation to complete the Gymnasium, Multipurpose and Cafeteria.
  • Roughing in underground electric, under slab drainage, plumbing and fire protection prior to the pouring of the first-floor slab.

Underground and sitework

  • Continuation of all underground utilities on the lower-level for water, electric, sanitary and fire service water mains.
  • Continued installation of stormwater structures on the north side of terrace four.
  • Start of excavation and grading of the northerly storm water retention basin.

What families will notice

  • The building is starting to take shape as the steel installation continues.
  • The elevator shaft rising to the West adjacent to the Gymnasium and Multipurpose rooms.
  • Excited students and staff after presentation by the Architect and Construction Manager.
  • Steel beam for students to sign which will be hoisted up into the building.

Coming up next

  • Remaining foundation pours for the cafeteria and Gymnasium should wrap up in the next few weeks.
  • Elevator CMU walls to be installed.
  • Complete prep for Lower-level floor slab pours expected to begin in November.
  • Erection of Structural steel and installation of metal decking to continue.

Source: Newfield Construction Group. Dates are projections and can shift with site conditions and inspections.

Next update

Late November

2026

Construction Time-Lapse

A bird's eye view of the build

Cameras on site compress weeks of work into twenty seconds each. New time-lapse clips are posted monthly as the building comes out of the ground; this footage covers June 24–October 23. Click any video to view it full screen.

Looking North — foundation walls and steel rising

Looking across the new building footprint: foundation walls poured one section at a time, with backfilling underway and the first steel rising.

Looking Southeast — beside the existing school

The view toward the current building, where the Gymnasium, Multipurpose and Cafeteria foundations are taking shape below grade.

Looking toward Hyde Lane — structural steel

Looking toward Hyde Lane with the existing school on the right: crews erect steel columns and beams, then install metal decking as the new building takes shape.

Want a closer look? To view photos of construction progress, visit our photos page.