Construction Updates as of September 16, 2026
Foundation work is nearing completion across the building footprint as crews finish the cafeteria and gymnasium sections, wrap up waterproofing, and prepare for the lower-level slab and structural steel.
What crews are doing right now
- Installing formwork for the final sections of the building foundation (cafeteria and gymnasium) and backfilling around completed sections.
- Continue installation of foundation and elevator pit waterproofing and insulation.
- Roughing in underground electric, plumbing and fire protection prior to the pouring of the first-floor slab.
Underground and sitework
- Installation of underground domestic and fire service water mains.
- Continued installation of stormwater structures on the north side of terrace four.
- Start of excavation and grading of the northerly storm water retention basin.
What families will notice
- Concrete and pump trucks on site most weekdays as the last foundation elements are placed.
- The full building footprint is now visible from Hyde Lane and neighboring streets.
- Construction entrance and fencing remain in their current locations.
Coming up next
- Remaining foundation pours should wrap up by early October.
- Elevator CMU walls to be installed.
- Lower-level floor slab pours expected to begin in October.
- Structural steel expected to begin once the underground utilities are completed and inspected.
Source: Newfield Construction Group. Dates are projections and can shift with site conditions and inspections.